Qualification Description
This qualification reflects the role of employees working in supervisory positions in civil construction. They perform tasks involving a broad range of varied activities most of which are complex and non-routine. They are responsible for the quantity and quality of the output of others, contribute to the development of technical solutions to non-routine problems and apply management plans to the workplace.
Licensing, legislative, regulatory and certification requirements that apply to this qualification can vary between states, territories, and industry sectors. Relevant information must be sourced prior to application of the qualification.
Entry Requirements
There are no entry requirements for this qualification.
Packaging Rules
Requirements for completion of the qualification
The following provides the packaging rules for this qualification, followed by the list of relevant units of competency.
Successful completion of twelve (12) units of competency made up of:
- five (5) core units, and
- seven (7) elective units of which:
- at least two (2) must be chosen from group A
- at least two (2) must be chosen from group B
- up to two (2) units may be chosen from Certificate III, Certificate IV or Diploma level from this, or any other Training Package or accredited course
Units chosen must be relevant to the job function.
There are both licensed and non-licensed units of competency relating to high risk work in the Resources and Infrastructure Industry Training Package. To be appointed under any statutory requirements in related roles, units of competency should be selected to meet the state/territory licensing requirements.
There are prerequisites to imported units listed in this qualification. Where a unit is imported as an elective care must be taken to ensure that all prerequisites specified are complied with.
Core units of competency |
|
Unit code |
Unit title |
BSBMGT401A |
Show leadership in the workplace |
BSBMGT402A |
Implement operational plan |
BSBWHS401A |
Implement and monitor WHS policies, procedures and programs to meet legislative requirements |
RIICWM401D |
Supervise civil works |
RIIRIS401D |
Apply site risk management system |
Electives |
|
Group A |
|
Unit code |
Unit title |
LGAWORK401A |
Develop works maintenance schedule |
LGAWORK402A |
Prepare for operational works |
MSL924001A |
Process and interpret data |
MSL975007A |
Supervise sampling, inspections and testing at construction sites
|
MSL975016A |
Perform complex tests to measure engineering properties of materials
|
RIIBLA401D |
Manage blasting operations |
RIIBLA402D |
Monitor and control the effects of blasting on the environment |
RIICBS401D |
Apply the principles for the asphalt paving and compaction |
RIICBS402D |
Apply the principles for the application of bituminous sprayed treatment |
RIICBS403D |
Apply the principles for the application of polymer modified binder |
RIICBS404D |
Apply the principles for the selection and use of bituminous emulsion |
RIICBS405D |
Apply the principles for the application of slurry surfacing |
RIICBS406D |
Apply the principles of pavement profiling using a profiler |
RIICBS407D |
Apply the principles for the manufacture and delivery of hot mix asphalt |
RIICBS408D |
Apply the principles for the manufacture of cold mix |
RIICBS409D |
Apply the principles for the manufacture of polymer modified binder |
RIICBS410D |
Apply the principles for the manufacture of bituminous emulsion |
RIICBS411D |
Apply the principles for the manufacture of slurry surfacing |
RIICPL401D |
Apply the principles for the installation of underground service using open excavation |
RIICRC401D |
Apply the principles of flexible pavement construction |
RIICRC402D |
Apply the principles of rigid pavement construction |
RIICRC403D |
Apply the principles of the stabilisation of materials |
RIICRC404D |
Inspect and report on pavement condition |
RIICRC405D |
Carry out pavement condition measurement |
RIICRC406D |
Apply the principles of pavement maintenance |
RIICSG401D |
Apply the principles of civil concrete structures construction |
RIICSG402D |
Apply the principles of civil steel structures construction |
RIICSG403D |
Apply the principles of civil timber structures construction |
RIICSG404D |
Apply the principles of civil masonry, crib and gabion structure construction |
RIICSG405D |
Carry out inspections of civil structures |
RIICSG406D |
Apply principles of maintenance of civil structures |
RIICTC401D |
Apply the principles of tunnel construction |
RIICTT401D |
Apply the principles for the installation of underground services using trenchless technology |
RIICTT402D |
Apply the principles for the repair and rehabilitation of underground services using trenchless technology |
RIICWD525D |
Select pavement surfacing |
RIICWM402D |
Supervise civil works contractors |
RIICWM503D |
Prepare civil works cost estimate |
RIICWM504D |
Prepare civil works bill of quantities |
RIICWM505D |
Prepare civil works schedule of rates |
RIIDML401D |
Apply the principles of demolitions |
RIIMEX403D |
Apply the principles of canal construction |
RIIMPO402D |
Apply the principles of earthworks construction |
Group B |
|
Unit code |
Unit title |
BSBCUS401B |
Coordinate implementation of customer service strategies |
BSBFIA402A |
Report on financial activity |
BSBFIM501A |
Manage budgets and financial plans |
BSBINM401A |
Implement workplace information system |
BSBINN301A |
Promote innovation in a team environment |
BSBLED401A |
Develop teams and individuals |
BSBMGT403A |
Implement continuous improvement |
BSBPMG413A |
Apply project human resources management approaches |
BSBPMG416A |
Apply project procurement procedures |
BSBPMG522A |
Undertake project work |
BSBSMB403A |
Market the small business |
BSBSMB404A |
Undertake small business planning |
BSBSMB402A |
Plan small business finances |
BSBSUS301B |
Implement and monitor environmentally sustainable work practices |
BSBWOR404B |
Develop work priorities |
LGADMIN417A |
Conduct community consultations |
LGACOM401A |
Administer contracts |
LGACOM402A |
Arrange contracts |
LGACOM409A |
Prepare tender documentation |
LGACOM410A |
Prepare response to tenders |
MSL953001A |
Receive and prepare samples for testing |
MSL973001A |
Perform basic tests |
MSL973002A |
Prepare working solutions |
MSL973006A |
Prepare trial batches for evaluation |
MSL974001A |
Prepare, standardise and use solutions |
PMLTEST403B |
Assist with geotechnical site investigations |
MSL974003A |
Perform chemical tests and procedures |
MSL974005A |
Perform physical tests |
MSL974010A |
Perform mechanical tests |
RIICCR401D |
Develop and maintain positive community relations |
RIICOM301D |
Communicate information |
RIICWD503D |
Prepare work zone traffic management plan |
RIIENV401D |
Supervise dust and noise control |
RIIGOV401D |
Apply, monitor and report on compliance systems |
RIIWHS302D |
Implement traffic management plan |
RIIWHS401D |
Supervise work in confined spaces |
RIIQUA401D |
Apply a quality management system on site |
RIIRAI402D |
Apply and monitor site plant and resource management plan |
RIIRIS301D |
Apply risk management processes |
RIIRIS403D |
Managing and coordinating spill response |
RIISAM401D |
Apply site plant, equipment and infrastructure management plan |
Qualification Mapping Information
No equivalent qualification
Links
Companion Volume implementation guides are found in VETNet - https://vetnet.gov.au/Pages/TrainingDocs.aspx?q=88a61002-9a21-4386-aaf8-69c76e675272