Unit of competency
Modification History
Release |
Comments |
Release 1 |
This version first released with ICT Information and Communications Technology Training Package Version 2.0. |
Application
This unit describes the skills and knowledge to effectively schedule the installation of customer premises equipment (CPE), including planning, provisioning and monitoring of customer premises installations.
It applies to individuals with a range of telecommunications skills, involves a degree of autonomy and may include limited supervision of others.
No licensing, legislative or certification requirements apply to this unit at the time of publication.
Unit Sector
Telecommunications – project management
Elements and Performance Criteria
Elements |
Performance Criteria |
Elements describe the essential outcomes |
Performance criteria describe the performance needed to demonstrate achievement of the element. |
1. Plan installation project |
1.1 Obtain relevant legislation, codes, regulations and standards, and follow work health and safety (WHS) and environmental requirements for given work 1.2 Plan work schedules for relevant parties to provision services and deliverables in correct sequence for satisfactory project completion within specified timeframe 1.3 Order materials in advance of needs to avoid work delays 1.4 Negotiate provision and connection of required network capacity and facilities with network provider 1.5 Determine customer equipment types and quantities, and organise timing of delivery according to work schedule timeframe 1.6 Determine essential criteria for selecting labour resources to satisfy regulatory, enterprise and customer requirements 1.7 Calculate installation workloads to complete task within specified timeframe |
2. Provision resources for installation project |
2.1 Arrange for connection of network services to customer equipment 2.2 Coordinate logistics associated with delivery of material to site according to installation timeframe 2.3 Allocate labour to installation as determined in planning stage 2.4 Ensure that all installation personnel are advised of installation and customer requirements |
3. Monitor and adjust resource allocations |
3.1 Adjust labour resources as necessary to meet budget and completion timeframe 3.2 Monitor work progress against project schedules and budgets |
Foundation Skills
This section describes language, literacy, numeracy and employment skills incorporated in the performance criteria that are required for competent performance.
Reading |
1.1, 1.5, 1.6 |
|
Writing |
1.2, 1.4, 1.5, 1.6, 2.1, 2.2, 2.4 |
|
Oral Communication |
1.4, 1.5, 1.6, 2.1, 2.2, 2.3, 2.4 |
|
Numeracy |
1.7, 2.2, 2.3, 3.2 |
|
Navigate the world of work |
1.1, 1.6 |
|
Get the work done |
1.1, 1.2, 1.3, 1.5, 1.6, 1.7, 2.1, 2.2, 2.3, 3.1, 3.2 |
|
Unit Mapping Information
Code and title current version |
Code and title previous version |
Comments |
Equivalence status |
ICTPMG402 Schedule installation of customer premises equipment |
ICTPMG4048A Schedule installation of customer premises equipment |
Updated to meet Standards for Training Packages |
Equivalent unit |
Links
Companion Volume implementation guides are found in VETNet - https://vetnet.gov.au/Pages/TrainingDocs.aspx?q=a53af4e4-b400-484e-b778-71c9e9d6aff2