Modification History
This version first released with CPC08 Construction, Plumbing and Services Training Package Version 9.
- Changes to unit title, elements and performance criteria, required skills and knowledge, range statement, critical aspects for assessment, and methods of assessment
- Range of other minor editorial changes
Not equivalent to CPCCCO3028A Carry out tilt panel construction
Unit Descriptor
This unit of competency specifies the outcomes required to work in a team to set up, pour and place concrete tilt panels to form internal and external walls for building structures.
The unit includes on-site and prefabricated methods of panel construction. It may also include working with others and as a member of a team.
Application of the Unit
This unit of competency supports the role of concreters responsible for constructing concrete tilt panels on residential, commercial or civil construction sites. Tilt panels can be used to construct internal and external walls of structures.
Licensing/Regulatory Information
Licensing, legislative, regulatory or certification requirements apply to concreting work in different states and territories. Candidates are advised to consult with the relevant regulatory authorities.
Pre-Requisites
CPCCOHS2001A |
Apply OHS requirements, policies and procedures in the construction industry |
Employability Skills Information
This unit contains employability skills.
Elements and Performance Criteria Pre-Content
Elements describe the essential outcomes of a unit of competency. |
Performance criteria describe the required performance needed to demonstrate achievement of the element. Where bold italicised text is used, further information is detailed in the required skills and knowledge and/or the range statement. Assessment of performance is to be consistent with the evidence guide. |
Elements and Performance Criteria
1 |
Plan and prepare. |
1.1 |
Work instructions, work health and safety (WHS) requirements and other information relevant to the work are identified, confirmed and applied for planning and preparation purposes. |
1.2 |
Plant, tools and equipment consistent with job requirements are selected and checked for serviceability, and faults are rectified and reported before work begins. |
||
1.3 |
Material quantity requirements are identified and calculated according to plans, specifications and quality requirements . |
||
1.4 |
Materials appropriate to the work application are obtained, prepared, safely handled and located ready for use. |
||
1.5 |
Environmental requirements are identified for the project according to environmental plans and regulatory obligations. |
2 |
Set out and construct temporary casting bed. |
2.1 |
Appropriate area is selected to construct casting bed according to project requirements. |
2.2 |
Ground is prepared to a flat surface in preparation for the casting bed. |
||
2.3 |
Casting bed is placed and finished to project requirements. |
||
2.4 |
Casting bed is coated with bond breaker according to product specifications. |
3 |
Set out and prepare formwork for panel. |
3.1 |
Location and size of tilt panel are set out to requirements of job drawings and specifications. |
3.2 |
Tilt panel edge formwork is prepared, placed and fixed plumb and aligned to specification. |
||
3.3 |
Bond breaker is applied to casting bed face or casting form face of previous panel to ensure ease of panel separation, according to manufacturer dose and quantity recommendations. |
||
3.4 |
Form release agent is applied to formwork according to specifications. |
4 |
Place and tie reinforcement and cast-in fittings. |
4.1 |
Reinforcement , accessories and cast-in fittings are checked for conformity with design and engineering specifications. |
4.2 |
Reinforcement, accessories and cast-in fittings are positioned exactly to engineer’s drawings and engineering specifications. |
||
4.3 |
Reinforcement is tied and/or welded in correct placement according to engineer’s drawings and specifications. |
5 |
Place, finish and cure concrete. |
5.1 |
Concrete is evenly placed and consolidated to specification using approved vibration method. |
5.2 |
Concrete surface is screeded and finished to specification ensuring cast-in fittings are clear. |
||
5.3 |
Curing process is applied according to specification. |
||
5.4 |
Bond breaker is applied to casting bed face of previous panel to ensure ease of panel separation. |
6 |
Clean up. |
6.1 |
Clean-up procedures are undertaken on a daily basis according to work site policies and procedures. |
6.2 |
Edge formwork is stripped after the final panel is cast, ensuring no damage to panels. |
||
6.3 |
Work area is cleared and materials disposed of, reused or recycled according to regulations, codes of practice and job specification. |
||
6.4 |
Plant, tools and equipment are cleaned, checked, maintained and stored according to manufacturer recommendations and standard work practices. |
Required Skills and Knowledge
This section describes the skills and knowledge required for this unit. |
Required skills |
|
Required knowledge |
|
Evidence Guide
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package. |
|
Overview of assessment |
This unit of competency could be assessed by undertaking a range of tasks in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures. |
Critical aspects for assessment and evidence required to demonstrate competency in this unit |
A person should demonstrate the ability to:
|
Context of and specific resources for assessment |
Assessment of this unit:
Resource implications for assessment include:
|
Method of assessment |
Assessment for this unit must verify the practical application of the required skills and knowledge, using a combination of the following methods:
|
Guidance information for assessment |
This unit could be assessed on its own or in combination with other units relevant to the job function. Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support. Assessment processes and techniques should, as far as is practical, take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed. |
Range Statement
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included. |
|
Work health and safety requirements must comply with state and territory legislation and regulations and project safety plan, and may include: |
|
Information may include: |
|
Planning and preparation must include: |
|
Tools and equipment : |
|
Quality requirements must include: |
|
Materials may include: |
|
Environmental requirements may include: |
|
Tilt panels may include: |
|
Formwork must include: |
|
Reinforcement components must include: |
|
Cast-in fittings may include: |
|
Placing methods for concrete may include: |
|
Finishing techniques for concrete may include: |
|
Curing may include: |
|
Unit Sector(s)
Concreting
Custom Content Section
Not applicable.