Modification History
Not Applicable
Unit Descriptor
Unit descriptor |
This unit of competency specifies the outcomes required to erect and dismantle slip form formwork to form wall structures where the formwork process is continuous. It includes curved or straight slip form formwork. |
Application of the Unit
Application of the unit |
This unit of competency supports achievement of skills for erecting and taking down slip form formwork for placing of concrete in a range of construction projects. Slip form formwork requires work as a member of a mixed trades team, including carpenters, riggers, electricians, concreters and steel fixers. |
Licensing/Regulatory Information
Not Applicable
Pre-Requisites
Prerequisite units |
CPCCOHS2001A Apply OHS requirements, policies and procedures in the construction industry |
Employability Skills Information
Employability skills |
This unit contains employability skills. |
Elements and Performance Criteria Pre-Content
Elements describe the essential outcomes of a unit of competency. |
Performance criteria describe the performance needed to demonstrate achievement of the element. Where bold italicised text is used, further information is detailed in the required skills and knowledge section and the range statement. Assessment of performance is to be consistent with the evidence guide. |
Elements and Performance Criteria
ELEMENT |
PERFORMANCE CRITERIA |
1. Plan and prepare. |
1.1. Work instructions, including plans, specifications, quality requirements and operational details, are obtained, confirmed and applied from relevant information for planning and preparation purposes. 1.2. Safety (OHS ) requirements are followed in accordance with safety plans and policies. 1.3. Signage and barricade requirements are identified and implemented. 1.4. Plant, tools and equipment selected to carry out tasks are consistent with job requirements, checked for serviceability, and any faults are rectified or reported prior to commencement. 1.5. Material quantity requirements are calculated in accordance with plans, specifications and quality requirements . 1.6. Materials appropriate to the work application are identified, obtained, prepared, safely handled and located ready for use. 1.7. Environmental requirements are identified for the project in accordance with environmental plans and statutory and regulatory authority obligations, and are applied. |
2. Set out formwork. |
2.1. Set out points and lines are located according to engineer's drawings, survey datum points and site plan for formwork erection. 2.2. Slip form formwork positioning is located to predetermined set out. |
3. Assemble core form system. |
3.1. Internal prefabricated system wall form shutters are erected and fixed into location according to engineer's drawings. 3.2. System is fitted to concrete nib walls to heights consistent with engineer's requirements. 3.3. Shear key feet are installed to manufacturer specifications. 3.4. Platforms and assembly are fitted into core to manufacturer specifications. 3.5. Structural steel system grid work and hydraulic hose lines are fitted to manufacturer specifications. 3.6. Wall form shutters are suspended and system cladding and platforms are fitted and completed to manufacturer specifications and engineer's requirements. |
4. Locate and install penetrations. |
4.1. Locations and dimensions of penetrations are set out in accordance with designated tolerance from engineering drawings. 4.2. Penetrations , block -outs and cast -in services are constructed where required to engineering drawings. 4.3. Penetrations are installed to requirements of engineering drawings. |
5. Conduct slip system. |
5.1. External prefabricated system wall shutters are erected and fixed to engineer's and manufacturer specifications. 5.2. Shutters are loosened and stripped according to manufacturer's and OHS requirements. 5.3. Rigger is communicated with to activate electrical/hydraulic jacking of the system to the new position. 5.4. Trailing platforms are installed to engineer's specifications. 5.5. Formwork is dismantled in accordance with manufacturer and engineer's specifications. |
6. Clean up. |
6.1. Work area is cleared and materials disposed of, reused or recycled in accordance with legislation, regulations, codes of practice and job specification. 6.2. Plant, tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and standard work practices. |
Required Skills and Knowledge
REQUIRED SKILLS AND KNOWLEDGE |
This section describes the skills and knowledge required for this unit. |
Required skills |
Required skills for this unit are:
|
Required knowledge |
Required knowledge for this unit is:
|
Evidence Guide
EVIDENCE GUIDE |
|
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package. |
|
Overview of assessment |
This unit of competency could be assessed in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures. |
Critical aspects for assessment and evidence required to demonstrate competency in this unit |
A person who demonstrates competency in this unit must be able to provide evidence of the ability to:
|
Context of and specific resources for assessment |
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints. Assessment of essential underpinning knowledge will usually be conducted in an off-site context. Assessment is to comply with relevant regulatory or Australian standards' requirements. Resource implications for assessment include:
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support. |
Method of assessment |
Assessment methods must:
Validity and sufficiency of evidence requires that:
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed. Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff. |
Range Statement
RANGE STATEMENT |
|
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included. |
|
Information includes: |
|
Planning and preparation include: |
|
Safety (OHS ) is to be in accordance with state or territory legislation, regulations, codes of practice, organisational safety policies and procedures, and project safety plan and may include: |
|
Tools and equipment include: |
|
Quality requirements include relevant regulations, including: |
|
Materials include: |
|
Environmental requirements include: |
|
Statutory and regulatory authorities include: |
|
Formwork : |
|
Slip form formwork : |
|
Penetrations , block -outs and cast -in services : |
|
Unit Sector(s)
Unit sector |
Construction |
Co-requisite units
Co-requisite units |
Nil |
Functional area
Functional area |