Unit of competency
Modification History
Release 1 |
This version first released with CPC Construction, Plumbing and Services Training Package Release 5.0. Supersedes and is equivalent to CPCCCA3008B Construct eaves. Updated to meet the Standards for Training Packages 2012. |
Application
This unit of competency specifies the skills and knowledge required to prepare, set out and construct eaves, including the cutting and fixing of fascia and barges to provide a finish between the wall and the roof, meeting all relevant requirements of the National Construction Code (NCC), Australian Standards, work health and safety (WHS), and Commonwealth and state or territory legislation.
The unit includes:
- construction of boxed and raked eaves
- finishing of gable ends including verge and flush.
Completion of the general construction induction training program specified by the model Code of Practice for Construction Work is required for any person who is to carry out construction work. Achievement of CPCCWHS1001Prepare to work safely in the construction industry meets this requirement.
No licensing, legislative or certification requirements apply to this unit at the time of publication.
Pre-requisite Unit
CPCCWHS2001 Apply WHS requirements, policies and procedures in the construction industry.
Unit Sector
Carpentry and Joinery
Elements and Performance Criteria
Elements describe the essential outcomes. |
Performance criteria describe what needs to be done to demonstrate achievement of the element. |
||
1 |
Plan and prepare. |
1.1 |
Read and interpret work instructions and plan sequence of work. |
1.2 |
Plan all work to comply with laws and regulations, the National Construction Code (NCC), Australian Standards, work health and safety (WHS) and environmental requirements, manufacturers’ specifications, workplace requirements, drawings and specifications. |
||
1.3 |
Select tools and equipment, check for serviceability and report any faults. |
||
1.4 |
Select and use personal protective equipment (PPE) as required for each stage of the task. |
||
1.5 |
Inspect work site, locate services, assess hazards and apply risk controls, including required signage and barricades. |
||
1.6 |
Select materials required for task, calculate quantities, handle safely and prepare and position ready for use. |
||
2 |
Construct framework for eaves or soffits. |
2.1 |
Determine eaves design from drawings and specifications and set out and fix framework. |
2.2 |
Set out, mark and cut timber and steel framework members to lengths for framework structure. |
||
2.3 |
Construct boxed eaves with soffit bearers and fix to line and level to wall frame or support by hangers from rafters/trusses. |
||
2.4 |
Set-out and install eave supports. |
||
3 |
Line and clad eaves and soffits. |
3.1 |
Mark and cut eaves cladding and sheeting material to shape to suit task application and jointing methods. |
3.2 |
Fit, join and fix eaves lining, cladding and soffits using methods for type of material and task application. |
||
3.3 |
Fit and fix mouldings to finish eaves. |
||
3.4 |
Fit raked eaves to rafters or framing. |
||
4 |
Clean up. |
4.1 |
Clean up, meeting all legislative and workplace requirements for safety, waste disposal and materials handling. |
4.2 |
Check, maintain and store tools and equipment and rectify or report any faults. |
Foundation Skills
Foundation skills essential to performance are explicit in the performance criteria of this unit of competency.
Unit Mapping Information
Supersedes and is equivalent to CPCCCA3008B Construct eaves.
Links
Companion Volume implementation guides are found in VETNet - https://vetnet.gov.au/Pages/TrainingDocs.aspx?q=7e15fa6a-68b8-4097-b099-030a5569b1ad