Unit of competency details

BSBPMG522A - Undertake project work (Release 1)

Summary

Usage recommendation:
Superseded
Mapping:
MappingNotesDate
Supersedes and is equivalent to BSBPMG510A - Manage projectsNew unit code. New unit title supported by industry to better reflect the outcomes of this unit, which had often been adopted in lieu of the broader project management units of competency. Added assessment context to “... demonstrate all required skills, knowledge and performance in a workplace-based project” to ensure alignment with vocational project practice. 17/Mar/2013
Is superseded by and equivalent to BSBPMG522 - Undertake project workUpdated to meet Standards for Training Packages 24/Mar/2015

Releases:
ReleaseRelease date
1 1 (this release) 18/Mar/2013

Training packages that include this unit

CodeSort Table listing Training packages that include this unit by the Code columnTitleSort Table listing Training packages that include this unit by the Title columnRelease
FPI11 - Forest and Forest Products Training PackageForest and Forest Products Training Package 2.0-2.3 
CPC08 - Construction, Plumbing and Services Training PackageConstruction, Plumbing and Services Training Package 9.0-9.2 
MSF - Furnishing Training PackageFurnishing Training Package 1.0-1.3 
MEM05 - Metal and Engineering Training PackageMetal and Engineering Training Package 10.1-11.1 
ICT10 - Integrated Telecommunications Training PackageIntegrated Telecommunications Training Package 3.0 
BSB07 - Business Services Training PackageBusiness Services Training Package 8.0-9.0 
FPP10 - Pulp & Paper Manufacturing Industry Training PackagePulp & Paper Manufacturing Industry Training Package 1.2-1.3 
CUV - Arts and Culture Training PackageArts and Culture Training Package 1.0 
DEF - Defence Training PackageDefence Training Package 1.0-2.0 
CUA - Creative Arts and Culture Training PackageCreative Arts and Culture Training Package 1.0 
RII - Resources and Infrastructure Industry Training PackageResources and Infrastructure Industry Training Package 1.0-1.4 
SFI11 - Seafood Industry Training PackageSeafood Industry Training Package 2.2 
RGR08 - Racing Training PackageRacing Training Package 2.0 

Qualifications that include this unit

CodeSort Table listing Qualifications that include this unit by the Code columnTitleSort Table listing Qualifications that include this unit by the Title columnUsage RecommendationRelease
MSF50213 - Diploma of Interior Design and DecorationDiploma of Interior Design and DecorationSuperseded
BSB41412 - Certificate IV in Work Health and SafetyCertificate IV in Work Health and SafetySuperseded2-3 
CUA50213 - Diploma of Musical TheatreDiploma of Musical TheatreSuperseded
BSB40812 - Certificate IV in Frontline ManagementCertificate IV in Frontline ManagementSuperseded2-3 
CUA50413 - Diploma of Live Production and Technical ServicesDiploma of Live Production and Technical ServicesSuperseded
BSB50613 - Diploma of Human Resources ManagementDiploma of Human Resources ManagementSuperseded
ICT50110 - Diploma of Optical NetworksDiploma of Optical NetworksSuperseded
BSB41807 - Certificate IV in Unionism and Industrial RelationsCertificate IV in Unionism and Industrial RelationsDeleted
FPI40411 - Certificate IV in Timber Truss and Frame DesignCertificate IV in Timber Truss and Frame DesignSuperseded3-4 
MSF60113 - Advanced Diploma of Interior DesignAdvanced Diploma of Interior DesignSuperseded1-2 
CUA50513 - Diploma of Live Production DesignDiploma of Live Production DesignSuperseded
BSB60612 - Advanced Diploma of Work Health and SafetyAdvanced Diploma of Work Health and SafetySuperseded
RII40713 - Certificate IV in Civil Construction SupervisionCertificate IV in Civil Construction SupervisionSuperseded1-3 
BSB51707 - Diploma of RecordkeepingDiploma of RecordkeepingSuperseded
BSB40407 - Certificate IV in Small Business ManagementCertificate IV in Small Business ManagementSuperseded3-4 
FPP50110 - Diploma of Pulp and Paper Process ManagementDiploma of Pulp and Paper Process ManagementSuperseded3-4 
SFI50211 - Diploma of Fishing OperationsDiploma of Fishing OperationsDeleted
BSB51107 - Diploma of ManagementDiploma of ManagementSuperseded
BSB50407 - Diploma of Business AdministrationDiploma of Business AdministrationSuperseded
BSB40212 - Certificate IV in BusinessCertificate IV in BusinessSuperseded
CPC40508 - Certificate IV in Building and Construction (Site Management)Certificate IV in Building and Construction (Site Management)Superseded4-5 
CPC40110 - Certificate IV in Building and Construction (Building)Certificate IV in Building and Construction (Building)Superseded4-5 
RGR50308 - Diploma of Racing Services (Steward)Diploma of Racing Services (Steward)Superseded
SFI50111 - Diploma of AquacultureDiploma of AquacultureSuperseded
BSB41707 - Certificate IV in RecordkeepingCertificate IV in RecordkeepingSuperseded
BSB50207 - Diploma of BusinessDiploma of BusinessSuperseded
CUA60213 - Advanced Diploma of Live Production and Management ServicesAdvanced Diploma of Live Production and Management ServicesSuperseded
CUA40213 - Certificate IV in Community CultureCertificate IV in Community CultureSuperseded
BSB50107 - Diploma of AdvertisingDiploma of AdvertisingSuperseded
ICT50410 - Diploma of Radio Frequency NetworksDiploma of Radio Frequency NetworksSuperseded
BSB50807 - Diploma of International BusinessDiploma of International BusinessSuperseded
BSB40312 - Certificate IV in Customer ContactCertificate IV in Customer ContactSuperseded
SFI50511 - Diploma of Seafood ProcessingDiploma of Seafood ProcessingDeleted
SFI50411 - Diploma of Fisheries ComplianceDiploma of Fisheries ComplianceSuperseded
FPI40311 - Certificate IV in Timber Truss and Frame ManufactureCertificate IV in Timber Truss and Frame ManufactureSuperseded3-4 
MEM60211 - Advanced Diploma of Jewellery and Object DesignAdvanced Diploma of Jewellery and Object DesignSuperseded
MEM50311 - Diploma of Jewellery and Object DesignDiploma of Jewellery and Object DesignSuperseded
FPI50111 - Diploma of Forest and Forest ProductsDiploma of Forest and Forest ProductsSuperseded
CPC40912 - Certificate IV in Plumbing and ServicesCertificate IV in Plumbing and ServicesSuperseded
ICT50210 - Diploma of Telecommunications Network EngineeringDiploma of Telecommunications Network EngineeringSuperseded
BSB51807 - Diploma of Unionism and Industrial RelationsDiploma of Unionism and Industrial RelationsDeleted
RGR50208 - Diploma of Racing Services (Racing Administration)Diploma of Racing Services (Racing Administration)Deleted
MSF40213 - Certificate IV in Furniture Design and TechnologyCertificate IV in Furniture Design and TechnologySuperseded
RGR40508 - Certificate IV in Racing Services (Racing Administration)Certificate IV in Racing Services (Racing Administration)Deleted
BSB50507 - Diploma of FranchisingDiploma of FranchisingSuperseded
CUV50613 - Diploma of Aboriginal and Torres Strait Islander Visual Arts Industry WorkDiploma of Aboriginal and Torres Strait Islander Visual Arts Industry WorkSuperseded
MSF50313 - Diploma of Furniture Design and TechnologyDiploma of Furniture Design and TechnologySuperseded
Items per page 10 | 20 | 50 | 100
Displaying items 1 - 47 of 47

Accredited courses that have this unit in the completion mapping

CodeSort Table listing Accredited courses that have this unit in the completion mapping by the Code columnTitleSort Table listing Accredited courses that have this unit in the completion mapping by the Title columnStatus
10500NAT - Certificate IV in Parent, Family and Community EngagementCertificate IV in Parent, Family and Community Engagement Non-Current
39295QLD - Diploma of Operational Management (Specialisation)Diploma of Operational Management (Specialisation) Non-Current
52559WA - Certificate IV in Leadership DevelopmentCertificate IV in Leadership Development Non-Current
10472NAT - Certificate IV in Community Development MinistryCertificate IV in Community Development Ministry Non-Current
10574NAT - Diploma of MinistryDiploma of Ministry Non-Current
22182VIC - Certificate IV in Tertiary PreparationCertificate IV in Tertiary Preparation Non-Current
10221NAT - Advanced Diploma of Industrial DesignAdvanced Diploma of Industrial Design Non-Current
10220NAT - Diploma of Industrial DesignDiploma of Industrial Design Non-Current
10375NAT - Certificate IV in Community and Post Disaster Program ManagementCertificate IV in Community and Post Disaster Program Management Non-Current
10428NAT - Diploma of Styling (Fashion, Image and Media)Diploma of Styling (Fashion, Image and Media) Non-Current
10035NAT - Certificate IV in Ministry (Insert Stream)Certificate IV in Ministry (Insert Stream) Non-Current
10546NAT - Diploma of Construction Material TestingDiploma of Construction Material Testing Non-Current
10036NAT - Diploma of Ministry (Insert Stream)Diploma of Ministry (Insert Stream) Non-Current
22284VIC - Diploma of Business (Public Relations)Diploma of Business (Public Relations) Non-Current
10368NAT - Diploma of Designing and Facilitating Corporate TrainingDiploma of Designing and Facilitating Corporate Training Non-Current

Classifications

SchemeCodeClassification value
ASCED Module/Unit of Competency Field of Education Identifier 080315 Project Management  

Classification history

SchemeCodeClassification valueStart dateEnd date
ASCED Module/Unit of Competency Field of Education Identifier 080315 Project Management  03/Oct/2013 
The content being displayed has been produced by a third party, while all attempts have been made to make this content as accessible as possible it cannot be guaranteed. If you are encountering issues following the content on this page please consider downloading the content in its original form

Modification History

Release 

Comments 

Release 1

This version first released with BSB07 Business Services Training Package Version 8.0.

Replaces BSBPMG510A Manage projects.

Unit Descriptor

This unit describes the performance outcomes, skills and knowledge required to undertake a straightforward project or a section of a larger project. This unit addresses the management of projects, including developing a project plan, administering and monitoring the project, finalising the project, and reviewing the project to identify lessons learned for application to future projects.

Application of the Unit

The unit focuses on the application of project-management skills and the requirement to meet timelines, quality standards, budgetary limits and other requirements set for the project.

The unit does not apply to specialist project managers. For specialist project managers, the other units of competency in the project management field (BSBPMG) will be applicable.

Licensing/Regulatory Information

No licensing, legislative, regulatory or certification requirements apply to this unit at the time of endorsement.

Pre-Requisites

Not applicable.

Employability Skills Information

This unit contains employability skills.

Elements and Performance Criteria Pre-Content

Element 

Performance Criteria 

Elements describe the essential outcomes of a unit of competency.

Performance criteria describe the performance needed to demonstrate achievement of the element. Where bold italicised text is used, further information is detailed in the required skills and knowledge section and the range statement. Assessment of performance is to be consistent with the evidence guide.

Elements and Performance Criteria

1. Define project

1.1 Access project scope and other relevant documentation 

1.2 Define project stakeholders

1.3 Seek clarification from delegating authority  of issues related to project and project parameters 

1.4 Identify limits of own responsibility and reporting requirements

1.5 Clarify relationship of project to other projects and to the organisation's objectives

1.6 Determine and access available resources to undertake project

2. Develop project plan

2.1 Develop project plan  in line with the project parameters

2.2 Identify and access appropriate project-management tools 

2.3 Formulate risk-management plan for project, including work health and safety (WHS)

2.4 Develop and approve project budget

2.5 Consult team members and take their views into account in planning the project

2.6 Finalise project plan and gain necessary approvals to commence project according to documented plan

3. Administer and monitor project

3.1 Take action to ensure project team members are clear about their responsibilities and the project requirements

3.2 Provide support for project team members , especially with regard to specific needs, to ensure that the quality of the expected outcomes of the project and documented time lines are met

3.3 Establish and maintain required record-keeping systems  throughout the project

3.4 Implement and monitor plans for managing project finances, resources  and quality

3.5 Complete and forward project reports as required to stakeholders

3.6 Undertake risk management  as required to ensure project outcomes are met

3.7 Achieve project deliverables

4. Finalise project

4.1 Complete financial record keeping associated with project and check for accuracy

4.2 Ensure transition of staff involved in project to new roles or reassignment to previous roles

4.3 Complete project documentation and obtain necessary sign-offs  for concluding project

5. Review project

5.1 Review project outcomes and processes against the project scope and plan

5.2 Involve team members in the project review

5.3 Document lessons learned from the project and report within the organisation

Required Skills and Knowledge

This section describes the skills and knowledge required for this unit.

Required skills 

  • communication and negotiation skills to work with team members and other stakeholders to maintain project schedules
  • communication skills to relate to people with diverse abilities and from diverse backgrounds in a culturally appropriate way
  • literacy skills to read, write and review a range of documentation
  • numeracy skills to:
  • analyse data
  • compare time lines and promotional costs against budgets
  • planning and organising skills to develop, monitor and maintain implementation schedules.

Required knowledge 

  • organisation's mission, goals, objectives and operations and how the project relates to them
  • organisational structure, and lines of authority and communication in the organisation
  • relevant legislation and codes from all levels of government that may affect aspects of business operations, including:
  • anti-discrimination legislation
  • codes of practice
  • environmental issues
  • ethical principles
  • WHS
  • privacy laws.

Evidence Guide

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment 

Critical aspects for assessment and evidence required to demonstrate competency in this unit 

Evidence of the following is essential:

  • developing a project plan
  • examples of monitoring arrangements and evaluation of the efficacy of the project plan in addressing project time lines and budget
  • knowledge of relevant legislation.

Context of and specific resources for assessment 

Assessment must ensure:

  • access to workplace project documentation
  • demonstration of all required skills, knowledge and performance in a workplace-based project.

Method of assessment 

A range of assessment methods should be used to assess practical skills and knowledge. The following examples are appropriate for this unit:

  • direct questioning combined with review of portfolios of evidence and third-party workplace reports of on-the-job performance by the candidate
  • observation of presentations
  • oral or written questioning to assess knowledge of the organisation's mission, goals, objectives and operations and how the project relates to them
  • review of project risk-management plan and project plan
  • evaluation of project reports forwarded to stakeholders
  • analysis of documentation reviewing project outcomes and processes against the project scope and plan
  • evaluation of documentation outlining lessons learned from the project.

Guidance information for assessment 

Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended, for example:

  • other project management units.

Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Project scope and other relevant documentation  may include:

  • contract or other agreement
  • project brief
  • project plan or summary
  • other documents outlining:
  • expected outcomes of the project
  • inclusions and exclusions from project
  • project resources
  • quality standards for project
  • timeframes for project.

Stakeholders  may include:

  • clients or customers (internal and external)
  • funding bodies
  • management, employees and relevant key personnel (internal and external) with special responsibilities
  • project sponsor.

Delegating authority  may include:

  • customer or client
  • funding body
  • manager or management representative
  • project sponsor.

Project parameters  may include:

  • project finances or budget
  • integration of project within organisation
  • legislative and quality standards
  • physical, human and technical resources available or required for project
  • procurement requirements associated with project
  • reporting requirements
  • risks associated with project, including WHS
  • scope of project
  • time lines.

Project plan  may include:

  • details of how the project will be managed
  • roles and responsibilities
  • time lines
  • work breakdown structure.

Project management tools  may include:

  • cost schedule control system
  • Critical Path Method
  • Gantt and bar charts
  • life cycle cost analysis
  • logistics support analysis
  • PERT charts
  • project management software
  • risk and issues logs
  • spreadsheets
  • technical resources required for the project, for example WHS management-system tools.

Support for project team members  may include:

  • additional physical, human and technical resources (within allocated budget) if and as required
  • encouragement
  • feedback
  • learning and development
  • regular project team meetings
  • supervision, mentoring and coaching.

Required record-keeping systems  may include systems for:

  • correspondence
  • financial data, including costs, expenditure, income generated and purchases
  • project outcomes
  • quality data, including any test results
  • recording of time spent on project and progress in completing project
  • samples, prototypes and models.

Resources  may include:

  • human
  • physical
  • technical.

Risk management  may include:

  • changing roles and responsibilities in project team
  • negotiating an extension of deadline, or redefining completion or quantity or quality of outcomes
  • outsourcing some aspects of the project
  • reducing costs
  • researching and applying more efficient methods for completing project tasks
  • seeking further resources to meet deadline
  • sharing ideas to gain improvements to work undertaken in the project.

Necessary sign-offs  may be required by:

  • clients
  • funding body
  • management
  • project sponsor.

Unit Sector(s)

Management and Leadership – Project Management