Unit Descriptor
Unit descriptor |
This unit covers the competence required to install air conditioning systems. Licensing, legislative, regulatory or certification requirements may apply to this unit in some jurisdictions. Users are advised to check with the relevant regulatory authority. |
Application of the Unit
Application of the unit |
Work involved includes installation of air conditioning systems fitted to light vehicles, plant and equipment, heavy vehicles or marine craft (low voltage). The unit includes identification and confirmation of work requirement, preparation for work, installation and charging of the air conditioning systems and completion of work finalisation processes, including clean-up and documentation. Work requires individuals to demonstrate discretion, judgement and problem-solving skills in managing own work activities and contributing to a productive team environment. |
Licensing/Regulatory Information
Not applicable.
Pre-Requisites
Not applicable.
Employability Skills Information
Employability skills |
This unit contains employability skills. |
Elements and Performance Criteria Pre-Content
Elements describe the essential outcomes of a unit of competency. |
Performance criteria describe the performance needed to demonstrate achievement of the element. Where bold italicised text is used, further information is detailed in the required skills and knowledge section and the range statement. Assessment of performance is to be consistent with the evidence guide. |
Elements and Performance Criteria
ELEMENT |
PERFORMANCE CRITERIA |
1. Prepare to install air conditioning systems |
1.1. Nature and scope of work requirements are identified and confirmed 1.2. WHS requirements, including individual State/Territory regulatory/licensing requirements and personal protection needs are observed throughout the work 1.3. Procedures and information such as schematic diagrams, manufacturer/component supplier instructions, workshop manuals and specifications, and tooling required, are sourced 1.4. Method options are analysed and those most appropriate to the circumstances are selected and prepared 1.5. Technical and/or calibration requirements for air conditioning components are sourced and support equipment is identified and prepared 1.6. Warnings in relation to working with air conditioning and refrigerants are observed |
2. Install air conditioning systems |
2.1. Correct information is accessed and interpreted from manufacturer/component supplier specifications 2.2. Fittings/materials are selected 2.3. Air conditioning systems are installed using tooling and techniques 2.4. Air conditioning system installation is completed without causing damage to any component or system 2.5. Installation is tested prior to placing in service and results are documented in accordance with enterprise policies and procedures 2.6. Installation is carried out according to industry regulations/ guidelines, WHS legislation, legislation and enterprise procedures/policies |
3. Charge air conditioning system with refrigerant and lubricating oil |
3.1. Correct information is accessed and interpreted from manufacturer/component supplier specifications, industry codes of practice and legislation 3.2. Charging of the air conditioning system is completed without causing damage to any component or system 3.3. System is performance tested using approved methods and equipment 3.4. Charging of the system is carried out according to manufacturer/component supplier specifications, industry regulations/guidelines, WHS legislation, legislation and enterprise policies/procedures |
4. Vehicle/equipment is prepared for deliver to customer |
4.1. Installation schedule documentation is completed 4.2. Final inspection is made to ensure protective guards, safety features and cowlings are in place 4.3. Final inspection is made to ensure the system is functional, without leaks and work is to workplace expectations 4.4. Vehicle/equipment is cleaned to workplace expectations 4.5. Job card is processed in accordance with workplace procedures |
Required Skills and Knowledge
REQUIRED SKILLS AND KNOWLEDGE |
This section describes the skills and knowledge required for this unit. |
Required skills |
|
Required knowledge |
A working knowledge of:
|
Evidence Guide
EVIDENCE GUIDE |
|
The evidence guide provides advice on assessment and must be read in conjunction with the Performance Criteria, required Skills and Knowledge, the Range Statement and the Assessment Guidelines for the Training Package. |
|
Overview of assessment |
|
Critical aspects for assessment and evidence required to demonstrate competency in this unit |
It is essential that competence in this unit signifies ability to transfer competence to changing circumstances and to respond to unusual circumstances in the critical aspects of:
|
Context of, and specific resources for assessment |
Application of competence is to be assessed in the workplace or simulated worksite Assessment is to occur using standard and authorised work practices, safety requirements and environmental constraints Assessment is to comply with regulatory requirements, including Australian Standards The following resources should be made available:
|
Method of assessment |
Assessment must satisfy the endorsed assessment guidelines of the automotive industry's RS&R Training Package Assessment methods must confirm consistency and accuracy of performance together with application of underpinning knowledge Assessment must be by direct observation of tasks, with questioning on underpinning knowledge and it must also reinforce the integration of key competencies Assessment may be applied under project related conditions and require evidence of process Assessment must confirm a reasonable inference that competence is able not only to be satisfied under the particular circumstance, but is able to be transferred to other circumstances It is preferable that assessment reflects a process rather than an event and occurs over a period of time to cover varying quality circumstances. Evidence of performance may be provided by customers, team leaders/members or other persons subject to agreed authentication arrangements Competence in this unit may be assessed in conjunction with other functional units which together form part of the holistic work role |
Range Statement
RANGE STATEMENT |
|
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included. |
|
Work requirements |
Work involved includes installation of air conditioning systems fitted to light vehicles, plant and equipment, heavy vehicles or marine craft (low voltage):
|
WHS |
WHS requirements are to be in accordance with legislation/regulations/codes of practice and enterprise safety policies and procedures. This may include protective clothing and equipment, use of tooling and equipment, workplace environment and safety, handling of material, use of fire fighting equipment, enterprise first aid, hazard control and hazardous materials and substances |
Personal protective equipment |
Personal protective equipment is to include that prescribed under legislation/regulations/codes of practice and workplace policies and practices |
Safe operating procedures |
Safe operating procedures are to include, but are not limited to the conduct of operational risk assessment and treatments associated with vehicular movement, toxic substances, electrical safety, machinery movement and operation, manual and mechanical lifting and shifting, working in proximity to others and site visitors |
Emergency procedures |
Emergency procedures related to this unit are to include, but are not limited to emergency shutdown and stopping of equipment, extinguishing fires, enterprise first aid requirements and site evacuation |
Environmental requirements |
Environmental requirements are to include but are not limited to waste management, noise, dust and clean-up management |
Quality requirements |
Quality requirements are to include, but are not limited to regulations, including Australian Standards, internal company quality policy and standards and enterprise operations and procedures |
Statutory /regulatory authorities |
Statutory/regulatory authorities may include Federal, State/Territory and local authorities administering acts, regulations and codes of practice |
Tooling and equipment |
Tooling and equipment may include hand tooling, refrigerant leak detecting equipment, refrigerant recovery and/or recycling equipment, thermometers, ram-air fan, refrigerant re-gassing equipment and air conditioning system kits |
Materials |
Materials may include spare parts, refrigerant, refrigerant oils and cleaning materials |
Communications |
Communications are to include, but are not limited to verbal and visual instructions and fault reporting and may include site specific instructions, written instructions, plans or instructions related to job/task, telephones and pagers |
Information /documents |
Sources of information/documents may include:
|
Unit Sector(s)
Unit sector |
Electrical |
Co-requisite units
Not applicable.
Competency field
Competency field |
Technical - Air conditioning and HVAC |