This Competency Standard Unit covers the maintenance of network protection and control systems in complex situations and includes isolation, inspection, monitoring, testing, adjustment, and repair, refurbishment and or overhaul and functional checks. It includes schemes from discrete and interdependent and also schemes such as, distance, differential, transformer differential, bus zone, bus overcurrent, revenue metering, SCADA, communications, harmonic control, point on wave. |
Application of the Unit
Application of the Unit |
2) |
This competency standards unit is intended to apply to any recognised development program that leads to the acquisition of a formal award at AQF level 6 or higher. |
Licensing/Regulatory Information
License to practice |
3) |
The skills and knowledge described in this unit may require a licence/registration to practice in the work place subject to regulations for undertaking of electrical work. Practice in workplace and during training is also subject to regulations directly related to Occupational Health and Safety, electricity/telecommunications/gas/water industry safety and compliance, industrial relations, environmental protection, anti discrimination and training. Commonwealth, State/Territory or Local Government legislation and regulations may exist that limits the age of operating certain equipment. |
Pre-Requisites
Prerequisite Unit(s) |
4) |
|
Competencies |
4.1) |
|
Granting of competency in this unit shall be made only after competency in the following unit(s) has/have been confirmed. Where pre-requisite pathways have been identified. All competencies in the Common Unit Group must be have been completed plus all the competencies in one (1) of the identified Pathway Unit Group(s): Common Unit Group |
||
Unit Code |
Unit Title |
|
UEENEED104A |
Use engineering applications software on personal computers |
|
UEENEEE101A |
Apply Occupational Health and Safety regulations, codes and practices in the workplace |
|
UEENEEE102A |
Fabricate, assemble and dismantle utilities industry components |
|
UEENEEE104A |
Solve problems in d.c. Circuits |
|
UEENEEE107A |
Use drawings, diagrams, schedules, standards, codes and specifications |
|
UEENEEE124A |
Compile and produce an energy sector detailed report |
|
UEENEEE125A |
Provide engineering solutions for problems in complex multiple path circuits problems |
|
UEENEEE126A |
Provide solutions to basic engineering computational problems |
|
UEENEEG101A |
Solve problems in electromagnetic devices and related circuits |
|
UEENEEG102A |
Solve problems in electromagnetic devices and related circuits |
|
UEENEEG149A |
Provide engineering solutions to problems in complex polyphase power circuits |
|
UETTDREL11A |
Apply sustainable energy and environmental procedures |
|
UETTDREL16A |
Working safely near live electrical apparatus |
|
UETTDRIS62A |
Implement and monitor the power system organisational OHS policies, procedures and programs |
|
UETTDRIS63A |
Implement and monitor the power system environmental and sustainable energy management policies and procedures |
|
UETTDRTS21A |
Maintain interdependent network protection and control systems |
|
UETTDRTS29A |
Develop power systems secondary isolation instructional documents |
Literacy and numeracy skills |
4.2) |
|||||
Participants are best equipped to achieve this unit if they have reading, writing and numeracy skills indicated by the following scales. Description of each scale is given in Volume 2, Part 3 “Literacy and Numeracy” |
||||||
Reading |
5 |
Writing |
5 |
Numeracy |
5 |
Employability Skills Information
Employability Skills |
5) |
The required outcomes described in this unit of competency contain applicable facets of Employability Skills. The Employability Skills Summary of the qualification in which this unit of competency is packaged will assist in identifying Employability Skill requirements. |
Elements and Performance Criteria Pre-Content
6) Elements describe the essential outcomes of a competency standard unit |
Performance Criteria describe the required performance needed to demonstrate achievement of the element. Assessment of performance is to be consistent with the Evidence Guide. |
Elements and Performance Criteria
ELEMENT |
PERFORMANCE CRITERIA |
||
1 |
Plan for the maintenance of network protection and control systems (complex) |
1.1 |
OHS practices/procedures and Environmental and sustainable energy procedures, which may influence the maintenance of, network protection and control systems (complex) are reviewed and determined. |
1.2 |
Purpose of the maintenance of network protection and control systems (complex) is established after data is analysed and expected outcomes of the work are confirmed with the appropriate personnel. |
||
1.3 |
Organisational established procedures on policies and specifications for the maintenance of network protection and control systems (complex) are obtained or established with the appropriate personnel. |
||
1.4 |
Testing procedures are discussed with and/or directed to the appropriate personnel in order to ascertain the project brief. |
||
1.5 |
Testing parameters are ascertained from organisational established procedures, policies and specifications |
||
1.6 |
Equipment/tools and personal protective equipment are selected based on specified Performance Criteria and established procedures. |
||
1.7 |
Work roles and tasks are allocated according to requirements and individuals’ competencies. |
||
1.8 |
Work is prioritised and sequenced for the most efficient/effective outcome, completed within an acceptable timeframe to a quality standard and in accordance with established procedures. |
||
1.9 |
Liaison and communication issues with other/authorised personnel, authorities, clients and land owners are resolved and activities coordinated to carry out work. |
||
1.10 |
Risk control measures are identified, prioritised and evaluated against the work schedule. |
||
1.11 |
Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures. |
||
2 |
Carry out the maintenance of network protection and control systems (complex) |
2.1 |
Circuit/systems modelling is used to evaluate alternative proposals as per established procedures. |
2.2 |
OHS and sustainable energy principles, functionality and practices to reduce the incidents of accidents and minimise waste are incorporated into the project in accordance with requirements and/or established procedures. |
||
2.3 |
Maintenance of network protection and control systems (complex) decisions are made on the basis of safety and effective outcomes according to requirements and/or established procedures. |
||
2.4 |
Mathematical and/or engineering models of the scheme are used to analyse the effectiveness of the finished project as per requirements and established procedures. |
||
2.5 |
Technical advice is given regarding potential hazards, safety risks and control measures so that monitoring and preventative action can be undertaken and/or appropriate authorities consulted, where necessary, in accordance with requirements and established procedures. |
||
2.6 |
Essential knowledge and associated skills are applied to analyse specific data and compare it with compliance specifications to ensure completion of the project within an agreed timeframe according to requirements. |
||
2.7 |
Testing of network protection and control systems (complex) is undertaken according to requirements and established procedures. |
||
2.8 |
Work teams/groups are arranged/coordinated/evaluated to ensure planned goals are met according to established procedures. |
||
2.9 |
Solutions to non-routine problems are identified and actioned, using acquired essential knowledge and associated skills, according to requirements. |
||
2.10 |
Quality of work is monitored against personal performance agreement and/or established organisational and professional standards. |
||
2.11 |
Strategic plans are developed incorporating organisation initiatives as per established procedures. |
||
3 |
Complete the maintenance of network protection and control systems (complex) |
3.1 |
Final inspections of the network protection and control systems (complex) are undertaken to ensure they comply with all requirements and include all specifications and documentation needed to complete the project. |
3.2 |
Appropriate personnel are notified of completion and reports and/or completion documents are finalised/commissioned. |
||
3.3 |
Reports and/or completion documents are submitted to relevant personnel/organisations for approval and, where applicable, statutory or regulatory approval. |
||
3.4 |
Approved copies of the maintenance of network protection and control systems (complex) documents are issued and records are updated in accordance with established procedures. |
Required Skills and Knowledge
REQUIRED SKILLS AND KNOWLEDGE |
8) Essential Knowledge and Associated Skills (EKAS): This describes the essential skills and knowledge and their level, required for this unit. Evidence shall show that knowledge has been acquired of maintaining network protection and control systems (complex). All knowledge and skills detailed in this unit should be contextualised to current industry practices and technologies. KS01-TTS35A Complex network protection and control systems Evidence shall show an understanding of complex network protection and control systems to an extent indicated by the following aspects: T1 Principles of power transformer construction and operations encompassing:
T2 Detailed operation of complex protection systems encompassing:
|
Evidence Guide
EVIDENCE GUIDE |
9) This provides essential advice for assessment of the unit of competency and must be read in conjunction with the Performance Criteria and the Range Statement of the unit of competency and the Training Package Assessment Guidelines. The Evidence Guide forms an integral part of this Competency Standard Unit and shall be used in conjunction with all component parts of this unit and, performed in accordance with the Assessment Guidelines of this Training Package. |
Overview of Assessment |
9.1) |
Longitudinal competency development approaches to assessment, such as Profiling, require data to be reliably gathered in a form that can be consistently interpreted over time. This approach is best utilised in Apprenticeship programs and reduces assessment intervention. It is the Industry’s preferred model for apprenticeships. However, where summative (or final) assessment is used it is to include the application of the competency in the normal work environment or, at a minimum, the application of the competency in a realistically simulated work environment. It is recognised that, in some circumstances, assessment in part or full can occur outside the workplace. However, it must be in accord with Industry and, Regulatory policy in this regard. Methods chosen for a particular assessment will be influenced by various factors. These include the extent of the assessment, the most effective locations for the assessment activities to take place, access to physical resources, additional safety measures that may be required and the critical nature of the competencies being assessed. The critical safety nature of working with electricity, electrical equipment, gas or any other hazardous substance/material carries risk in deeming a person competent. Hence, sources of evidence need to be ‘rich’ in nature so as to minimise error in judgment. Activities associated with normal every day work have a bearing on the decision as to how much and how detailed the data gathered will contribute to its ‘richness’. Some skills are more critical to safety and operational requirements while the same skills may be more or less frequently practiced. These points are raised for the assessors to consider when choosing an assessment method and developing assessment instruments. Sample assessment instruments are included for Assessors in the Assessment Guidelines of this Training Package. |
Critical aspects of evidence required to demonstrate competency in this unit |
9.2) |
|||
Before the critical aspects of evidence are considered all prerequisites shall be met. Evidence for competence in this unit shall be considered holistically. Each element and associated Performance Criteria shall be demonstrated on at least two occasions in accordance with the “Assessment Guidelines – UET12”. Evidence shall also comprise:
|
||||
Range of tools/equipment/materials/procedures/workplaces/other variables |
||||
Group No |
The minimum number of items on which skill is to be demonstrated |
Item List |
||
A |
Do all of the following: Note: Utilise different schemes from within the complex schemes in the Range Statement of this unit. |
Isolate protection, control and alarms associated with complex protection and control schemes. Calibrate complex protection and control relays. Carry out function tests (Trips, alarms etc.) on complex protection and control schemes. Write reports on performance of complex protection and control schemes. Isolate ‘in service’ Current Transformers. |
||
B |
Do all of the following: |
Activities that address the correction of errors in network protection and control systems |
||
C |
At least one occasion |
Dealing with an unplanned event by drawing on essential knowledge and associated skills to provide appropriate solutions incorporated in the holistic assessment with the above listed items. |
Context of and specific resources for assessment |
9.3) |
This unit should be assessed as it relates to normal work practice using procedures, information and resources typical of a workplace. This should include:
In addition to the resources listed above, in Context of and specific resources for assessment, evidence should show demonstrated competency working in realistic environment and a variety of conditions. |
Method of assessment |
9.4) |
This Competency Standard Unit shall be assessed by methods given in Volume 1, Part 3 “Assessment Guidelines”. Note: Competent performance with inherent safe working practices is expected in the Transmission, Distribution and Rail Traction Industry. This requires that the specified essential knowledge and associated skills are assessed in a structured environment which is primarily intended for learning/assessment and incorporates all necessary equipment and facilities for learners to develop and demonstrate the essential knowledge and associated skills described in this unit. |
Concurrent assessment and relationship with other units |
9.5) |
There are no concurrent assessment recommendations for this unit. |
Range Statement
RANGE STATEMENT |
10) This relates to the unit of competency as a whole providing the range of contexts and conditions to which the Performance Criteria apply. It allows for different work environments and situations that will affect performance. This Competency Standard Unit shall be demonstrated in relation to the maintenance of network protection and control systems (complex) and may include the following: Discrete: Overcurrent, earth fault, frame leakage, cooling, buchholz, DC supplies, restricted earth, sensitive earth fault, reclose, DC frame leakage, CEL fail under frequency load shed. Interdependent :Instrument transformers, trip/control circuits, alarms, DC supplies, CB fail protection, master controlled earth fault, intertripping, blocking, synchronising, pilot wire, phase comparison, load shedding, voltage control, parallel operation, load rejection, circuit isolations and restorations, mechanical adjustments, calibration, function tests, reporting, signals, thermals, contraphase, backup, reverse current Complex: distance, differential, transformer differential, bus zone, bus overcurrent, revenue metering, SCADA, communications, harmonic control, point on wave. The following constants and variables included in the element/Performance Criteria in this unit are fully described in the Definitions Section 1 of this volume and form an integral part of the Range Statement of this unit:
|
Unit Sector(s)
Not applicable.
Competency Field
Competency Field |
11) |
Testing Units |