Unit of competency details

PUAEMR024 - Develop treatment options for emergency risk (Release 1)

Summary

Usage recommendation:
Superseded
Mapping:
MappingNotesDate
Is superseded by and equivalent to PUAEMR003 - Develop treatment options for emergency risk 15/Jul/2019
Supersedes and is equivalent to PUAEMR003B - Determine treatment strategies 16/Aug/2012

Releases:
ReleaseRelease date
1 1 (this release) 17/Aug/2012

Qualifications that include this unit

CodeSort Table listing Qualifications that include this unit by the Code columnTitleSort Table listing Qualifications that include this unit by the Title columnUsage RecommendationRelease
DEF42415 - Certificate IV in Explosive Ordnance OperationsCertificate IV in Explosive Ordnance OperationsSuperseded
DEF42215 - Certificate IV in Explosive Ordnance Proof and ExperimentalCertificate IV in Explosive Ordnance Proof and ExperimentalSuperseded
DEF52115 - Diploma of Explosive OrdnanceDiploma of Explosive OrdnanceSuperseded
DEF42315 - Certificate IV in Explosive Ordnance ManufactureCertificate IV in Explosive Ordnance ManufactureSuperseded
DEF50717 - Diploma of Range Control and ManagementDiploma of Range Control and ManagementSuperseded
DEF50712 - Diploma of Range ManagementDiploma of Range ManagementSuperseded
DEF52315 - Diploma of Explosive Ordnance Proof and ExperimentalDiploma of Explosive Ordnance Proof and ExperimentalSuperseded
DEF55115 - Diploma of Range ManagementDiploma of Range ManagementSuperseded
DEF50317 - Diploma of ComplianceDiploma of ComplianceCurrent
DEF52312 - Diploma of Work Health SafetyDiploma of Work Health SafetyDeleted
Items per page 10 | 20 | 50 | 100
Displaying items 1 - 10 of 12

Classifications

SchemeCodeClassification value
ASCED Module/Unit of Competency Field of Education Identifier 080313 Public And Health Care Administration  

Classification history

SchemeCodeClassification valueStart dateEnd date
ASCED Module/Unit of Competency Field of Education Identifier 080313 Public And Health Care Administration  03/Dec/2012 
The content being displayed has been produced by a third party, while all attempts have been made to make this content as accessible as possible it cannot be guaranteed. If you are encountering issues following the content on this page please consider downloading the content in its original form

Modification History

Release 

TP version 

Comments 

1

PUA12 V1

First release.

Unit Descriptor

This unit describes the outcomes required to determine a range of treatment options which can be used to reduce emergency risk.

Application of the Unit

This unit applies to people who are part of a working group that develops treatment options during an emergency risk assessment with a community or part of a community. Such assessments are conducted at local, regional or state level by local governments, emergency management committees, public safety agencies, major event managers or other organisations that need to understand emergency risk to a community.

No licencing, legislative, regulatory or certification requirements apply to this unit at the time of publication.

Licensing/Regulatory Information

Not applicable.

Pre-Requisites

Not applicable.

Employability Skills Information

This unit contains employability skills.

Elements and Performance Criteria Pre-Content

Elements describe the essential outcomes of a Unit of Competency.

Performance Criteria describe the required performance needed to demonstrate achievement of the element. Where bold italicised  text is used, further information is detailed in the Range Statement. Assessment of performance is to be consistent with the Evidence Guide.

Elements and Performance Criteria

ELEMENT 

PERFORMANCE CRITERIA 

Elements describe the essential outcomes of a Unit of Competency.

Performance Criteria describe the required performance needed to demonstrate achievement of the element. Where bold italicised  text is used, further information is detailed in the Range Statement. Assessment of performance is to be consistent with the Evidence Guide.

1. Identify treatment options 

1.1 Risk treatment objectives are identified in consultation with stakeholders .

1.2 Existing risk treatment options  are identified through research and stakeholder consultation.

1.3 A range of potential risk treatment options are identified through research and stakeholder consultation.

2. Evaluate options 

2.1 Evaluation methods  are agreed with stakeholders.

2.2 Feedback on likely implications and impacts of treatment options is obtained from stakeholders.

2.3 Residual risks are assessed for tolerability or acceptance

2.4 Cost-benefit analysis is completed for each risk treatment option.

3. Recommend treatment options 

3.1 Recommended options, including implementation responsibilities, are agreed in consultation with stakeholders.

3.2 Recommended options and residual risk are documented according to organisational policies and procedures .

3.3 Recommended options are submitted for approval in line with organisational policies and procedures.

4. Develop treatment plan 

4.1 Treatment options, resources required, milestones, budget, reporting procedures and roles and responsibilities for implementation are identified.

4.2 Communication and project management strategies are developed with stakeholders.

4.3 Implementation issues are identified and contingencies developed where necessary.

4.4 An agreed treatment plan is documented and submitted for approval in accordance with organisational policies procedures.

Required Skills and Knowledge

This describes the essential skills and knowledge and their level, required for this unit.

Required Skills 

  • Research and analysis skills to determine potential treatment options
  • ability to negotiate and work effectively with stakeholder groups
  • analytical techniques to determine residual risk
  • analytical techniques to conduct benefit:cost analysis at an appropriate level

Required Knowledge 

  • emergency risk management concepts and principles included in the current National Emergency Risk Assessment Guidelines and AS/NZS ISO 31000:2009 Risk management—Principles and Guidelines
  • legislative and regulatory requirements relevant to emergency risk management
  • jurisdiction and organisational documentation and submission procedures
  • analytical, problem solving and decision making techniques to facilitate evaluating residual risk and cost-benefit analysis
  • geospatial databases and presentation options
  • range of options for treating emergency risk

Evidence Guide

Critical aspects for assessment and evidence required to demonstrate competency in this unit 

Candidates must demonstrate an ability to work with stakeholders and generate an agreed list of recommended treatment options in an appropriate format.

Consistency in performance 

Candidates should be expected to present evidence from at least two different contexts, one of which may be simulated.

Context of and specific resources for assessment 

Context of assessment 

Evidence of competence in this unit may be collected in a simulated environment and real environment, often as part of a larger project with concurrent assessment of other emergency risk management competencies.

Specific resources for assessment 

For the demonstration of competence in this unit it will be necessary to participate in a real-world project.

Underpinning knowledge may be assessed through written assignments, project reports, debriefings and action learning projects in real or simulated environments.

Guidance information for assessment  

This unit contains many transferable skills, such as communication, consultation, research and analysis skills that can be applied in the emergency risk management context. Assessors should use formative assessment strategies in a simulated environment to contextualise underpinning knowledge. Summative assessment requires application of the unit in a real-world project, often in an action-learning project.

This unit may be assessed with other units that address other parts of the emergency risk management process.

Range Statement

The Range Statement relates to the Unit of Competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised  wording in the Performance Criteria is detailed below.

Stakeholders  may include:

  • staff
  • client groups
  • decision makers
  • members of the public
  • community groups
  • industry groups
  • public and private sector organisations
  • non-government organisations
  • elected officials

Risk treatment options  may include:

  • avoidance of the risk
  • removing a risk source
  • changing the likelihood of
  • an initiating event or source of risk occurring
  • a hazard impacting on elements at risk
  • changing the consequences of an identified hazard impact
  • sharing the risk
  • retaining the risk based on an informed decision

Evaluation methods  may include:

  • first-pass cost-benefit analysis
  • analysis of treatment effectiveness
  • potential to create new or secondary risks
  • stakeholder acceptability
  • legal, regulatory and compliance impact

Policies and procedures  may include:

  • arrangements specified in legislation
  • organisational or jurisdictional emergency risk management policies or procedures
  • existing disaster plans, agreements or memoranda of understanding

Unit Sector(s)

Not applicable.

Custom Content Section

Not applicable.