Application
This unit of competency specifies the outcomes required to process building applications for buildings included in Building Code of Australia (BCA) definitions for:
- classes 2 to 9 (up to three storeys), and
- three-storey class 1 buildings.
The unit covers gathering and assessing documentation that supports the building application process, which if successful, results in the issuing of a building permit.
The unit supports the work of private and municipal building surveyors carrying out the statutory role of ensuring that proposed commercial building projects meet relevant compliance requirements prior to commencement of construction.
Licensing, legislative, regulatory or certification requirements apply to this unit in some States. Relevant state and territory regulatory authorities should be consulted to confirm those requirements.
Pre-requisite Unit
Nil
Competency Field
Building surveying
Unit Sector
Construction
Elements and Performance Criteria
Elements describe the essential outcomes. |
Performance criteria describe the performance needed to demonstrate achievement of the element. Where bold italicised text is used, further information is detailed in the range of conditions. |
||
1. |
Plan and prepare to assess building application. |
1.1. |
Nature and scope of building application are reviewed and relevant legislation, codes and local planning policies are accessed. |
1.2. |
Specific building approval timelines and administrative requirements of the relevant local authority are identified and clarified. |
||
1.3. |
Proposed development site is inspected where necessary, to assist in understanding the nature of the development and potential impact on surrounding environment and structures. |
||
1.4. |
Need for advice from external consultants with specialist expertise is identified and relevant consultants are liaised with to provide advice throughout the building application process. |
||
1.5. |
Aspects of the application requiring consents or approvals from service authorities are identified and initiated. |
||
2. |
Assess building application documentation. |
2.1. |
Documentation received in support of building application is reviewed for accuracy, currency and completeness according to local authority requirements, and further information is requested from client where necessary. |
2.2. |
Property ownership is confirmed with reference to titles and other relevant documentation. |
||
2.3. |
Documentation submitted is assessed for compliance with current and relevant local planning scheme, codes and legislation, and areas of non-compliance are documented for discussion with client. |
||
2.4. |
Site of proposed building application is reviewed for possible environmental protection laws and exclusions, and compliance requirements are noted and documented for discussion with client. |
||
2.5. |
Design plans are assessed for compliance with relevant legislation, codes and regulations, and areas of non-compliance are documented for discussion with client, architect or building designer. |
||
2.6. |
Required amendments to plans to ensure compliance and proposed alternative solutions are documented and communicated to client. |
||
3. |
Assess revised design plans. |
3.1. |
Revised plans and documentation re-submitted for building approval are assessed for compliance. |
3.2. |
Design features requiring clarification are discussed with client, architect or building designer as necessary to ensure plans meet compliance requirements. |
||
3.3. |
Client is updated on progress of the building application process as necessary. |
||
4. |
Finalise building permission. |
4.1. |
Public notices are arranged according to local authority requirements, and objections are documented and handled according to regulations and workplace procedures. |
4.2. |
Final building permit is processed, including relevant permission conditions that ensure protection of the environment, adjacent structures and where appropriate, heritage listed structures. |
||
4.3. |
Copy of building permit is submitted to local authority and client as required. |
Foundation Skills
This section describes the language, literacy, numeracy and employment skills essential to performance in this unit but not explicit in the performance criteria. |
|
Skill |
Performance feature |
Learning skills to: |
|
Numeracy skills to: |
|
Oral communication skills to: |
|
Reading skills to: |
|
Writing skills to: |
|
Range of Conditions
This section specifies work environments and conditions that may affect performance. Essential operating conditions that may be present (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) are included. Bold italicised wording, if used in the performance criteria, is detailed below. |
|
Consultants must include at least one of the following: |
|
Service authorities must include: |
|
Documentation must include: |
|
Unit Mapping Information
No equivalent unit.
Links
Companion Volume implementation guides are found in VETNet - https://vetnet.gov.au/Pages/TrainingDocs.aspx?q=7e15fa6a-68b8-4097-b099-030a5569b1ad